Project Timeline & Milestones
Your implementation follows a structured deployment schedule. Each phase includes site verification, equipment validation, and stakeholder sign-offs.
Site Preparation & Permitting
Finalize zoning approvals, grid interconnection agreements, and site clearance. Civil works initiated.
Equipment Delivery & Staging
PV modules, inverters, battery arrays, and mounting structures delivered to site. Quality inspection completed.
Core Installation & Wiring
Structural mounting, electrical conduit routing, inverter placement, and DC/AC wiring. Daily progress reports submitted.
Commissioning & Testing
System energization, performance ratio verification, SCADA integration, and safety inspections.
Client Handover & Training
Documentation transfer, operator training, portal access activation, and warranty registration.
Implementation Checklist
Track your action items and required sign-offs. Click checkboxes to mark completion.
-
Review & approve final engineering drawings
-
Sign site access & safety compliance forms
-
Provide utility interconnection approval letter
-
Schedule mid-installation walkthrough
-
Verify storage system battery placement clearance
Technical Specifications & Scope
This section outlines the exact hardware, software, and integration parameters approved in Phase 2.
Energy Generation
- Solar Array: 1.2 MWp Monocrystalline Bifacial Modules (Tier 1)
- Wind Turbines: 2x 850kW Micro-Hydro Hybrid Units
- Inverters: 4x 300kW String Inverters with MPPT Optimization
Storage & Grid Integration
- Battery System: 500kWh Lithium Iron Phosphate (LFP) Racks
- Smart Controller: Verdantix EnergyOS v3.2 with AI Load Balancing
- Monitoring: Real-time SCADA dashboard & mobile API access